Savannah Ocean Terminal renovation
Savannah, Georgia· Reviewed 2026-09-19
What’s happening here
Second berth targeted June 2026; yard renovation first half 2027 and full completion by end-2028
Nearly $1.6B berth, gate, yard and building program was 55% complete in June 2026
- Project owner
- Georgia Ports Authority
- Known construction partner
- Design-build packages advertised by Georgia Ports Authority; package-level awards vary
- Current phase
- Active construction
- Construction workforce context
- Not establishedGeorgia Ports source gives project cost and schedule but not current workforce count
Trades relevant to the work
Inferred: marine concrete, dredging, cranes, steel, paving, utilities, electrical, buildings, traffic systems and rail/yard work
These are trades associated with the project scope, not a verified list of current vacancies.
Per diem & other perks
No current, project-specific incentive package was confirmed in this research. Ask the hiring employer about per diem, lodging, travel, overtime, and attendance conditions for the exact assignment.
Explore sourced incentive examplesJobs at this project
Loading project-linked listings…
Job listings are separate from project activity. An active construction site does not establish a current opening.
Post a job for this projectWhat still needs confirming
- Current contractor roster
- Trade-by-trade staffing
- Remaining berth and yard package sequence
- Public craft hiring contacts