Energy & LNGUnder construction
Plaquemines LNG
Plaquemines Parish, Louisiana· Reviewed 2026-09-18
What’s happening here
Phase I COD target Q4 2026; Phase II mid-2027; brownfield expansion subject to approvals/FID
- Project owner
- Venture Global
- Known construction partner
- Venture Global in-house/EPC partners
- Current phase
- active construction/commissioning; expansion planned
- Construction workforce context
- thousands at peak for expansion; current count unknownowner statement is direct construction jobs at peak, not current headcount
Project scale is not an opening count.Workforce figures can describe peak crews, long-term employment, or operations jobs. Current positions must be confirmed through the hiring organization.
Trades relevant to the work
LNG trains, power island, tanks, piping, welding, electrical/instrumentation, heavy lift, commissioning
These are trades associated with the project scope, not a verified list of current vacancies.
Per diem & other perks
No current, project-specific incentive package was confirmed in this research. Ask the hiring employer about per diem, lodging, travel, overtime, and attendance conditions for the exact assignment.
Explore sourced incentive examplesJobs at this project
Loading project-linked listings…
Job listings are separate from project activity. An active construction site does not establish a current opening.
Post a job for this projectWhat still needs confirming
- Current Phase I/II crew
- Expansion FID
- Contractor packages
Go straight to the sources
Venture Global Q2 2026 resultsVenture Global · Publication date not stated · Reviewed 2026-09-18
Plaquemines brownfield expansionVenture Global · Published 2025-03-06 · Reviewed 2026-09-18