Data centersConstruction & preconstruction
Meta Hyperion
Richland Parish, Louisiana· Reviewed 2026-09-18
What’s happening here
Broke ground Dec 2024; Phase 1 buildings began 2025; Phase 2 preconstruction through June 2027
- Project owner
- Meta
- Known construction partner
- Turner, DPR, Mortenson identified for major scopes
- Current phase
- active multi-building build; Phase 2 preconstruction
- Construction workforce context
- ~7,500 peak; >1,000 permanentTurner July 2026 expanded-campus estimate; earlier Meta page said 5,000 peak/>500 operations
Project scale is not an opening count.Workforce figures can describe peak crews, long-term employment, or operations jobs. Current positions must be confirmed through the hiring organization.
Trades relevant to the work
Earthwork, concrete, steel, electrical distribution, cooling, fire protection, fiber, controls, commissioning
These are trades associated with the project scope, not a verified list of current vacancies.
Per diem & other perks
No current, project-specific incentive package was confirmed in this research. Ask the hiring employer about per diem, lodging, travel, overtime, and attendance conditions for the exact assignment.
Explore sourced incentive examplesJobs at this project
Loading project-linked listings…
Job listings are separate from project activity. An active construction site does not establish a current opening.
Post a job for this projectWhat still needs confirming
- Current concurrent workforce
- Phase 2 award timing
- Subcontractor hiring
Go straight to the sources
Expanded Meta data center creates more jobsTurner Construction · Published 2026-07-16 · Reviewed 2026-09-18
Richland Parish data center resource pageTurner Construction · Publication date not stated · Reviewed 2026-09-18
One Year In: Richland Parish Data CenterMeta · Published 2025-12-19 · Reviewed 2026-09-18