All projects
ManufacturingUnder construction

Ford BlueOval Battery Park Michigan

Marshall, Michigan· Reviewed 2026-09-19

What’s happening here

Ford progress report June 2025; LFP and energy-storage battery production targeted for 2026

Ford reported the structure complete with process mechanical, electrical and piping work underway; production target is 2026

Project owner
Ford
Known construction partner
Unknown
Current phase
active build-out / commissioning
Construction workforce context
Not establishedFord's reviewed progress report does not give a current construction headcount.
Project scale is not an opening count.Workforce figures can describe peak crews, long-term employment, or operations jobs. Current positions must be confirmed through the hiring organization.

Trades relevant to the work

Process mechanical, piping, electrical, cleanroom, controls, equipment installation and commissioning inferred from Ford's build-out description.

These are trades associated with the project scope, not a verified list of current vacancies.

Per diem & other perks

No current, project-specific incentive package was confirmed in this research. Ask the hiring employer about per diem, lodging, travel, overtime, and attendance conditions for the exact assignment.

Explore sourced incentive examples

Jobs at this project

Loading project-linked listings…

Job listings are separate from project activity. An active construction site does not establish a current opening.

Post a job for this project

What still needs confirming

  • Current construction crew, trade contractors and open craft roles unknown.
  • Battery ownership/use has changed over time; this record is the Marshall plant only.

Go straight to the sources

Ford-owned American LFP battery plant paves wayFord · Published 2025-06-23 · Reviewed 2026-09-19
Ford Sustainability Statements 2026Ford · Publication date not stated · Reviewed 2026-09-19